Overhead Cranes
M-41A

Tag Number MAB 41 - 10.1Tag Description Monorail Crane (electrical)
System Code HST-952System Description Mech Handling MAB41
Sub-System Code HST-952-42Sub-System Description MAB 41 - 10.1
Main Area Description Location CAS
No. Description of Check / Action to be completed OK P/L NA
1
Confirm that civil work is complete in accordance with AFC Drawings & Red Line delivered.
2
Confirm that surrounding area is backfilled and compacted to the correct level, surveyed & all deliverables available
3
Confirm that all surface gravel paving is complete and accepted, surveyed & all deliverables available
4
Confirm that all Quality Documents have been completed, accepted and attached (where necessary).
5
Confirm Punch List Walk down has been completed and recorded.
6
Self Inspections Carried Out
7
Materials Receipts / Certificates
8
Measurement Data
9
Test Certificates
10
Inspection Reports (According to ITP Steps / Area)
11
Handover Certificates (Leaving Contractor)
12
RAMS / MS
13
NCRs / QOCs
14
ITPs - Signed Off
15
Signature List
16
Casting Journal (Reception Control / Testing / Delivery Slips)
17
Continuity Measurements (Grounding)
18
Temperature Measurements (Concrete)
19
Product Data Sheets for Embedded Items